5
elements of a binding contract
21days
HDB option period, expiring at 4 pm
8%a year
late completion interest (Condition 9)
3years
longest lease with full effect at 18 (s 35 Civil Law Act)

1What a binding contract needs

Terms must be certain. For property, check the 3Ps: Parties, Property, Price.

Elements

  • Offer and acceptance
  • Consideration (or a deed)
  • Intention to create legal relations
  • Capacity
  • Legal object
Land is the exception · s 6(d) Civil Law Act 1909Most contracts can be oral. But a contract for the sale or other disposition of immovable property (or an interest in it) cannot be sued on unless it, or a memorandum or note of it, is in writing and signed by the party to be charged or someone he authorised. An oral land deal is unenforceable, not void (subject to part performance).

2Offer and acceptance

Acceptance must be unconditional, on the same terms, and communicated.

Invitation to treatlistings, adverts, price-tagged displays, auctions, tender notices
invites▸
Offerdefinite promise to be bound once accepted
accepted▸
Contractunconditional, same terms
An offer ends by
Withdrawal before acceptanceRejectionCounter-offerLapse of timeFailed conditionDeath

Withdrawal

Must reach the offeree; news from a reliable third party is enough.

Keeping it open

Binds only if paid for (an option fee) or made by deed.

Counter-offer

Rejects the offer for good. A request for information is not one.

Silence

Generally not acceptance, even if the offeror says so.

Postal rule

Complete on posting if posting is reasonable or invited, unless receipt is required. Not instant communication; email unsettled.

Prescribed mode

If mandatory, no other mode binds. An OTP states how and by when to exercise.

Key ruleOffering the full asking price is still only an offer.

3Consideration, deeds and intention

Something of value in law, or a deed, plus intention.

Consideration

Sufficient, not necessarily adequate: $1 is enough. Past consideration is no consideration.

Deed

Needs no consideration: a gift of property, a free release.

Commercial

Intention presumed (including an estate agency agreement).

Social and domestic

Presumed not binding; rebuttable (separated spouses).

“Subject to contract”No one is bound until the formal document is signed. A lease LOI is usually subject to the TA, but an accepted LOI can still bind its own terms (forfeiting the good-faith deposit).

4Capacity and legality

Age under s 35 Civil Law Act, then incapacity and illegality.

ContractFull effect from
Most contracts; lease up to 3 years18
Sale, purchase, mortgage, assignment or settlement of land; lease over 3 years21

Mental incapacity, drunkenness

Voidable if he could not understand and the other knew or ought to have known.

Illegality

Not enforced. Foreign person buying in breach of s 3 Residential Property Act 1976: void.

Backdated OTP

Ting Siew May [2014] SGCA 28: backdated to get around MAS’s loan-to-value notice. Unenforceable at common law (the notice itself did not prohibit the option); no specific performance.

5Valid, void, voidable, unenforceable

Name the status, then the property example.

StatusMeaningExample
ValidEnforceable by both.OTP exercised in time.
VoidNo contract at all.Foreigner buying restricted property without approval; unit already destroyed.
VoidableValid until the innocent party rescinds; he may affirm.S&P induced by misrepresentation, undue influence or duress.
UnenforceableValid, but not enforced.Oral land sale; claim over 6 years after it accrued (Limitation Act).
Revoke an offerRescind a voidable contractRepudiate: refuse to perform

6Mistake, undue influence and duress

Mistake can make a contract void; pressure makes it voidable.

MistakeWhat happenedEffect
CommonSame fundamental false assumption (chalet burned down the day before).Void
MutualAt cross purposes; objective test.Usually no effect; void only if no objective agreement
UnilateralFundamental term; the other actually knows (or deliberately shuts his eyes).Void at common law
Non est factumRadically different document; signer not careless.Void
Digilandmall [2005] SGCA 2Buyers who knew $66 for a laser printer was an error could not enforce it.
When did the problem arise?
At contracting
Common mistakeVoid if the shared mistake is fundamental.
After contracting
FrustrationIf nobody’s fault and performance is impossible or radically different: discharged automatically.

Undue influence (voidable)

Actual, or presumed from trust (parent and child, lawyer and client) where the deal calls for explanation. Stronger party must prove free will.

Duress (voidable)

Threats of violence or illegitimate economic pressure leaving no real choice.

7Conditions, warranties, innominate terms

A false term is a breach; a false representation is misrepresentation.

ConditionWarrantyInnominate
NatureGoes to the root: vacant possession for an own-stay buyer, price.Minor: leaving curtains.Breach could be trivial or serious.
On breachDischarge or affirm; damages either way.Damages only.Discharge only if substantially the whole benefit is lost.

8Misrepresentation and disclosure

A false statement of fact that induced the contract.

Actionable

  • False statement of past or existing fact
  • By one party to the other
  • Induced the contract
  • Spoken or written

Not actionable

  • Puffs
  • Opinions: “worth $1.5M” (unless not actually held, or the speaker has special knowledge and no reasonable basis)
  • Predictions
  • No reliance
Caveat emptorGenerally no duty to disclose, especially physical defects (but a seller must disclose latent defects in title). A half-truth, a false answer to a direct question, or a statement that has become untrue before contracting is a misrepresentation.
TypeState of mindRemedies
FraudulentKnew it was false, or reckless.Rescission and damages for deceit.
NegligentCannot prove reasonable grounds for belief (s 2(1)).Rescission and damages as of right.
InnocentHonest belief on reasonable grounds.Rescission; discretionary damages in lieu (s 2(2)).

Losing rescission (s 1)

Affirmation, delay, third-party rights, or cannot restore.

Exclusion clause (s 3)

No effect unless reasonable; the party relying on it proves that.

Salespersons

Code of Ethics: never mislead; opinions on verifiable facts. Verify before stating.

9Four ways a contract is discharged

Performance, agreement, breach, frustration.

1

Performance

Exact; for a sale, at completion.

2

Agreement

Both still owe: mutual release binds. Only one owes: release needs fresh consideration or a deed.

3

Breach

Repudiatory breach does not end it automatically: accept or affirm. Anticipatory: no need to wait.

4

Frustration

Nobody’s fault; ends automatically, no damages.

Frustration?

  • Compulsory acquisition gazetted after contracting (unless the contract provides for acquisition, as many options do)
  • Lost job or loan
  • Price fall
Frustrated Contracts Act, s 2Money paid is recoverable; the court may let the payee keep part, up to his expenses.

10Remedies

Damages as of right; the rest equitable or targeted.

RemedyKey points
DamagesAs of right. Not too remote (Hadley v Baxendale); must mitigate. Liquidated: pre-agreed.
Specific performanceDiscretionary; suits land (each property unique). Refused if damages adequate, unfair to third parties, hardship, or claimant acted improperly.
InjunctionStop breaching a negative promise (unlawful subletting).
RescissionSets aside a voidable contract.
RestitutionPrevents unjust enrichment.
RectificationCorrects a misrecorded document (wrong unit number).

11Privity, third parties and assignment

Only parties can sue, unless the 2001 Act lets a third party in.

Third party (s 2)

Enforces if the contract expressly allows or the term purports to benefit him, and he is expressly identified, unless the contract shows otherwise.

Locked in (s 3)

After his assent or foreseeable reliance, no variation or rescission without his consent, unless the contract says so. Promisee keeps his own right (s 5).

Benefit: assignable

  • Without consent, unless prohibited or personal
  • After notice, paying the old creditor does not discharge

Burden: not assignable

  • Needs a novation, all three consenting
  • Developer’s option: cannot be assigned

12OTP and S&P

An OTP is the seller’s irrevocable offer, held open for the option fee.

OTP grantedbuyer pays the option fee
exercised in time▸
Contract of saleConditions of Sale: “Contract” includes an exercised option
balance paid▸
Completiontransfer delivered
Not exercisedOption lapses; seller keeps the option fee and may sell to anyone.
HDB resaleDeveloperCompleted private
FormHDB-prescribed OTP onlyPrescribedNone prescribed
FeesOption $1 to $1,000; with exercise not over $5,000Booking fee 5% to 10%Commonly 1% + 4% (residential)
Option period21 calendar days, expiring 4 pm3 weeks from the day after delivery of the S&P and title documentsCommonly 14 days

Private figures

Market practice, not law.

Cheque stopped or dishonoured

After exercise, seller may treat it as repudiation and rescind, or affirm (Condition 4).

Conditional contract

Binds; a failed condition depends on its wording.

13Law Society’s Conditions of Sale 2020

Apply only if incorporated; special conditions prevail (Condition 17).

ConditionKey rule
1Completion date on a weekend or public holiday: next Business Day.
5State at the option or contract date, whichever is earlier, fair wear and tear excepted.
6, 7Seller takes rents, pays outgoings and property tax up to and including the Scheduled Completion Date. Unpaid SSD: buyer deducts it.
9Party solely at fault: 8% a year, from the day after the Scheduled Completion Date up to and including actual completion. Buyer pays on price less deposit and any part payment; seller on the price.
9.5Death or loss of mental capacity before the Scheduled Completion Date: postpone a reasonable period, not more than 3 months from the death or loss of capacity; no interest; contract continues.
10Seller warrants no unauthorised additions or alterations.
13Risk passes on completion or possession, whichever is earlier.
Interest example$1,000,000 price, $50,000 deposit, 10 days late: $950,000 × 8% × 10/365 = $2,082.19.
Notice to Complete · Condition 15Unless time is made of the essence, missing the date alone does not allow forfeiture. Either party may serve; effective only if the giver is ready, able and willing to complete, or is not only because of the other side’s default (15.6).
Seller waits 5 clear Business Days
21 days: time of the essence
Mode of payment givenNotice served21 days after service

Buyer defaults

Seller may forfeit the deposit, resell and recover any loss on a resale within 1 year after the Scheduled Completion Date.

Seller defaults

Buyer may seek specific performance, or deposit back plus damages (then specific performance is lost).

14Ending the deal and getting a solicitor

Completed, rescinded or repudiated.

Completed: balance paid, transfer deliveredRescinded: set asideRepudiated: refuses to perform
Before signingTime to read, explain consequences; money agreements in writing, no blanks in essential terms.
Get a solicitor
Special conditionsTitle problemsDoes a contract exist?Notices to CompleteRescission, misrepresentationDeath or incapacityConveyancing

Common traps

Read these the night before.

A listing is an invitation to treat. The buyer’s message is the offer, even at the full asking price.
A counter-offer kills the original offer. “I’ll think about it” and silence are not acceptance.
A deadline does not stop withdrawal unless an option fee was paid (or a deed).
Sufficient, not adequate: $1 is good consideration; past help is not.
Misrepresentation, undue influence, duress: voidable. Backdated OTP: unenforceable, not voidable.
Before or after? Before: common mistake. After: frustration. A lost job or loan is neither.
s 2(1) damages are as of right unless the maker had reasonable grounds; s 2(2) damages are discretionary.
Risk passes on completion or possession, whichever is earlier, not on exercise.
Missing the completion date is not enough to forfeit. Serve an effective Notice to Complete.
HDB caps ($1,000, $5,000, 21 days) do not apply to private property.
From 1 January 2027The contract unit is broadly unchanged but adds express vs implied terms, exemption clauses and the purpose of an indemnity clause. See the full notes.

Read the full Lessons 5–6 notes free

The full notes cover every point in detail, with the law and CEA references. Create a free account with just your email. No password and no payment. You also get one chapter of practice questions free.

Sign up freeAlready have an account? Sign in

Our own summary. Figures checked against official sources on 3 October 2026.

Practise Lessons 5–6Exam-style questions at three levels, with an explanation for every answer.
Practise this chapter →

Want the full set?

Option to Pass has 1,850+ original questions across all 16 chapters at three levels, 80+ case studies and two full mock papers in the real exam format. Lesson 1A is free, with no sign-up.